Abbott Road, MP 0.25 to MP 0.50
Installing sidewalk on the north side of the road and eliminating stormwater outfalls to Yellowhawk Creek.
Updates:
Project is complete
Vicinity Map
Detour Map
CRP Number:
20-04
Funding Source:
TIB/County
Project Cost:
$475,000
Construction Date:
August 2022
Completion Date:
December 2022
Project Documents:
- Call for Bid
- Plan Holders List
- Plans
- Specifications
- Addendums
- Bid Tab
- Bid Award
Contact Information:
Seth Walker, PE
Chief of Engineering and Construction