Abbott Road, MP 0.25 to MP 0.50

Installing sidewalk on the north side of the road and eliminating stormwater outfalls to Yellowhawk Creek.

Dell Sharpe Bridge on Pettyjohn Road, MP 5.20 to MP 5.80
Replace existing bridge with a two-span, prestressed girder bridge.

Fishhook Park Road, MP 0.00 to MP 1.40
Fishhook Park Road will be widened and overlaid to provide paved shoulders. Clear zone will be provided with delineation.

Lower Waitsburg Road, MP 4.23 to MP 6.25
Lower Waitsburg Road will be realigned and widened to meet current design standards and provide clear zone.

Middle Waitsburg Road, MP 6.10 to MP 7.92
Realign existing road to remove substandard horizontal and vertical curves. Widen road to provide paved shoulders and remove deficient guardrail. Flatten slopes and provide clear zone, provide delineation with edge stripe.

Mill Creek Flood Control Project
Notice is hereby posted to inform the public of the upcoming rehabilitation to the Mill Creek levee system. This rehabilitation is to restore damages sustained during the February 2020 flood events.

Mill Creek Road Project, MP 1.1 to MP 3.96
This project realigns Mill Creek Road at 5 Mile Road beginning near Harbert Road matching into the construction completed just past Seven Mile Road. 5 Mile Road will also be realigned to match into Mill Creek Road which will be relocated  to the top of the hill.

Peppers Bridge Road, MP 0.36 to MP 1.61
Peppers Bridge Road will be widened and overlaid to provide paved shoulders and reconstruct two vertical curves to meet current sight distance standards. Culverts will be lengthened and /or beveled with proper end treatments. Clear zone will be provided with delineation.

Seven Mile Bridge, on Seven Mile Road, MP 2.30 to MP 2.55
Replace existing bridge with a two-span, prestressed girder bridge.

Wallula Avenue, MP 2.00 to MP 2.20
Reconstruct intersection to include compact roundabout and sidewalks.