Dodd Road Project
This project will improve 6.34 miles of Dodd Road, as follows: cleaning concrete joints, crack sealing, planing bituminous pavement, overlay with HMA, and rebuild existing HMA shoulders, and other work, all in accordance with the Contract Plans, Special Provisions, and the Standard Specifications.
CRP Number:
16-07
Updates:
We awarded the construction contract to Inland Asphalt of Tri-Cities. The first working day is March 13, 2017. Construction should be substantially complete in 30 working days or by April 21, 2017. The work from Highway 12 (milepost 0.00) to IBP, Inc. (milepost 1.00) will be performed during the first two weekends (March 18 & 19 and 25 & 26).
Please follow construction signs and flaggers and expect delays during construction.